2025 Construction Update: Construction funding is contingent on the Anchorage Roads and Drainage Service Area (ARDSA) bond passing on April 1, 2025. If funding is secured then construction is anticipated to begin in approximately July 2025. Additional contact information announcing the Contractor and the PM&E Project Inspector will be provided if funding is secured.
The Municipality of Anchorage Project Management & Engineering Department (MOA PM&E) is planning to upgrade Quinhagak Street between East Dowling Road and Askeland Drive (see map below for project limits). Improvements will include:
- New road foundation
- New asphalt pavement
- New curb & gutter
- New storm drain system
- New pedestrian facilities
- New street lighting
MOA PM&E has contracted with CRW Engineering Group, Inc. (CRW) to provide engineering and design services. The project is funded only through the design phase.
How to get involved:
- Sign up for e-mail updates by clicking the link at the bottom of this page.
- Contact us anytime with comments or questions at justin.keene@crweng.com and holly@huddleak.com
Recent Project News
Current Project Schedule
UPCOMING MEETINGS
Anchorage Transportation Fair
Tuesday, April 15th, 2025
Drop by anytime between 3:00 PM and 7:00 PM.
Alaska Airlines Center, Auxiliary Gym
3550 Providence Drive
More Information
PAST MEETINGS & DOCUMENTS
December 2024
Pre-Final 95% Plans
October 2024
Open House #3
Graphics Presented
Map of the Project Area
